State of Kansas

Department of Transportation

Notice to Contractors

Electronic copies of the letting proposals and plans are available on the Kansas Department of Transportation (KDOT) website at https://kdotapp.ksdot.org/Proposal/Proposal.aspx. The website will allow the contractor to request approval from KDOT to bid as a prime contractor and be included on the “Bid Holders List,” or to be included on the “Non-Bid Holders List” as a subcontractor/supplier. KDOT’s approval is required to bid as a prime contractor. To bid as a prime contractor, KDOT needs to be notified of the intent to bid no later than the close of business on the Monday preceding the scheduled letting date. Failure to obtain prior approval to bid as a prime contractor on any projects listed below will be reason to reject your bid. The Secretary reserves the right to reject bids that do not comply with all requirements for preparing a bidding proposal as specified in the 2015 edition of the Kansas Department of Transportation Standard Specifications for State Road and Bridge Construction.

KDOT will only accept electronic internet proposals using the Bid Express website at https://bidx.com/ks/main until 1:00 p.m. (Central Time) on letting day. The KDOT bid letting will be conducted remotely by audio broadcast ONLY at 3:00 p.m. (Central Time) on letting day. For the conference call information see https://www.ksdot.org/bureaus/burconsmain/lettinginfo.asp. KDOT has tested the process, but in the event of an unforeseen issue, KDOT will provide updates.

Each bidder shall certify that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the submitted bid. This certification shall be in the form of a required contract provision provided by the state to each prospective bidder. Failure to complete the required contract provision and certify the completeness of the preceding statement when electronically signing the proposal will make the bid nonresponsive and not eligible for award consideration.

Projects for the July 19, 2023 Letting

District One – Northeast

Johnson – 46 N-0703-01 – City of Gardner, South Center Street bridge over BNSF and west side of North Center Street from West Shawnee Street to West McKinley Street, pedestrian and bicycle paths, 0.3 mile. (Federal Funds)

Lyon – 99-56 KA-6991-01 – K-99, from K-170/K-99 junction north to US-56/K-99 junction, sealing, 9.1 miles. (State Funds)

Shawnee – 470-89 KA-5766-01 – I-470, bridge #046 located 0.2 miles northwest of 10th Street, bridge replacement. (Federal Funds)

Statewide – 170-106 KA-6988-01 – K-170; from the junction K-99/K-170 east to the Lyon/Osage County line in Lyon County, sealing, and from the Osage/Lyon County line east to the south city limits of Osage City in Osage County, sealing, 21.4 miles. (State Funds)

District Two – North Central

Statewide – 106 KA-7127-01 – US-81, from the Ottawa/Cloud County line north to Eagle Road; I-135 from the Saline/McPherson County line north to the US-40/I-70/I-135 junction, rumble strip installation, 23.9 miles. (State Funds)

District Three – Northwest

Norton – 60-69 KA-7000-01 – K-60, from the US-36/K-60 junction north to the end of K-60, sealing, 4.3 miles. (State Funds)

Osborne – 281-71 KA-7004-01 – US-281, from the County Road 412/US-281 junction north to the south city limits of Osborne, sealing, 16 miles. (State Funds)

Rawlins – 77 C-5134-01 – Major collector routes, east of K-25 in Rawlins County, signing, 121.9 miles. (Federal Funds)

Sherman – 91 KA-7058-01 – Comfort station, along I-70 by the city of Goodland at the K-27/I-70/US-24B junction and the Road 21/I-70/US-24B junction, special. (State Funds)

District Four – Southeast

Montgomery – 169-63 KA-5989-01 – US-169, from 0.3 mile south of 15th Street north 0.2 miles, pavement reconstruction, 0.2 mile. (Federal Funds)

District Five – South Central

Harvey – 15-40 KA-6997-01 – K-15, from the north city limits of Newton north to the Harvey/Marion County line, sealing, 7.6 miles. (State Funds)

Kingman – 14-48 KA-6922-01 – K-14, from the K-42/K-14 junction north to the south city limits of Kingman, crack repair, 12.1 miles. (State Funds)

Reno – 50-78 KA-6790-01 – US-50, light towers located north of US-50 0.2 mile and east of Scott Boulevard, lighting, 0.7 mile. (State Funds)

Rice – 4-80 KA-6916-01 – K-4, from the Barton/Rice County line east to the Rice/Ellsworth County line, crack repair, 25.4 miles. (State Funds)

Sedgwick – 54-87 KA-6179-01 – US-54, in Wichita between West Street and Armour Street, intelligent transportation system, 7.7 miles. (State Funds)

Sedgwick – 54-87 KA-6770-01 – US-54, bridge #132 located 0.2 mile east of Hoover Road, bridge repair. (State Funds)

Sedgwick – 235-87 KA-6918-01 – I-235, from the I-235/I-135 junction in Wichita north to North Broadway Street, pavement marking, 15.6 miles. (Federal Funds)

Sedgwick – 96-87 KA-7060-01 – K-96, from 0.7 mile east of Webb Road to the north approaches of bridges over US-54, 4-inch overlay, 4.6 miles. (State Funds)

Sumner – 81-96 KA-6921-01 – US-81, from 2.5 miles north of RS 645 north to the south city limits of Wellington, and from the north city limits of Wellington north to the Sumner/Sedgwick County line, crack repair, 18.9 miles. (State Funds)

District Six – Southwest

Greeley – 96-36 KA-6994-01 – K-96, from the K-27/K-96 junction east to the Greeley/Wichita County line, sealing, 10.2 miles. (State Funds)

Hodgeman – 156-42 KA-7003-01 – K-156, from the Finney/Hodgeman County line, east to Road 214, sealing, 14.6 miles. (State Funds)

Scott – 95-86 KA-6996-01 – K-95, from the US-83/K-95 south junction north to the US- 83/K-95 north junction, sealing, 6.6 miles. (State Funds)

Wichita – 25-102 KA-6444-01 – K-25, from 0.03 mile north of K-96 to I Street, pavement reconstruction, 0.1 miles. (Federal Funds)