Volume 44 - Issue 15 - April 10, 2025
(Published in the Kansas Register April 10, 2025.)
South Kansas & Oklahoma Railroad
Request for Proposals
Interested parties are invited to submit a proposal to complete the below scope of work for the South Kansas & Oklahoma (SKOL) Railroad.
Scope of Work
Upgrade 21,120 linear feet of 115RE CWR and plates from the existing 9020. Plugging compound is required. Contractor is responsible for compound plug.
Minimum Requirements
MSA and Roadway Worker Protection
- Contractors must complete, and have on file, a current Master Services Agreement with SKOL Railroad prior to starting work. Prior to submitting a proposal.
- Contractors shall always comply with all parts of 49 CFR Part 214 and 219 regarding FRA Roadway Worker Safety. Workers and equipment shall remain clear of the track unless they have gained Roadway Worker Protection from a qualified person.
- Contractor, contractor employees, agents, and/or subcontractors must be enrolled and comply with the FRA 219 approved drug testing program.
- Any sub-contracted work will need to be approved by the SKOL Railroad prior to any work starting.
- All contractors will be required to complete WATCO Contractor Orientation at https://watcocontractor.com. Any contractor who was previously enrolled in e-SHORTLINE with WATCO in the past, will be required to complete the WATCO Contractor Orientation. A RWIC qualified roadway worker must be on site at all times. This qualification can be obtained through the WATCO contractor website.
Work Windows
8 to 10-hour windows with possibility of one interruption per day.
Standards
All standards referenced by the project plans and specifications, as well as all applicable AREMA standards must be upheld during all phases of the project work, unless certain standards are excluded from the project with written approval by the SKOL Railroad. All rails shall be replaced at standard gauge of 56-1/2.” Switches must meet FRA 213 standard for guard check gage for Class 2 at 54-1/4.”
Submittals
The following documents shall be submitted by the contractor as part of the project at the times listed:
- Schedule of Work – Submitted with proposal.
- Certificate of Insurance – Submitted prior to construction.
- Safety Plan – Submitted prior to construction.
- Proof of Roadway Worker Training – Submitted prior to construction.
Other Responsibilities
- Permits – Contractor is responsible for all federal, state, and local permits required for the work. Additional permit information will be covered at the pre-proposal meeting.
- Utilities – Contractor is responsible to locate and protect site utilities.
- Site Clean-up – Contractor is responsible for proper site restoration and proper disposal of materials, trash, containers, etc., must be disposed of in accordance with all local, state, and federal laws.
Insurance
Contractor shall purchase required coverage and submit for verification a Certificate of Insurance.
Materials
All materials shall meet the requirements found in the project plans and/or specifications as well as applicable AREMA requirements. Material storage is granted on railroad right of way to the contractor. However, no materials shall be stored closer than 15’ feet from the centerline of any active track at any time. Material and equipment laydown areas and reclaimed materials stockpiling locations shall be discussed and further clarified at the pre-proposal meeting. All removed materials will be disposed of accordingly by the contractor unless otherwise arranged with the SKOL Railroad.
Non-Project Areas
The SKOL Railroad has secured access to the project through the railroad right of way. Other access may be obtained by the contractor if he/she so chooses. All areas (public, private, and railroad right of way) that are used for access to the project, including parts of the railroad right of way which have no proposed work, shall be maintained and/or remediated, incidental to the project, by the contractor to the satisfaction of the property owner if any damage to these areas occurs.
Pre-Proposal Meeting
The SKOL Railroad (Watco) shall hold a pre-proposal meeting at 1:00 p.m. April 22, 2025, to address any questions or clarify any portions of the project tasks. Please reach out to Mike Mulnix for specific meeting details.
Project Completion
It is expected the contractor must start construction no later than 60 days after being awarded the bid (dependent upon material deliveries) and complete the project within an agreed upon timeline. Prior to the completion of the project, there will be a 3rd party final inspection. If there are any issues with the quality of work, the contractor will be responsible for fixing any issues found at cost to them. A NTP is in effect on this project – planned construction timeline is slated for completion in May 2024.
Submission of a Proposal
All proposals must be submitted no later than 4:00 p.m. April 29, 2025. All submitted proposals shall be reviewed by the SKOL Railroad. Please ensure your proposal includes all required information. All incomplete proposals shall be rejected. The structure of your proposal must be able to be clearly understood, all proposals shall provide the following line items and provide costs as required below:
Provide a total sum of all Line Items on the proposal:
- Mobilization and Demobilization – Lump sum.
- Labor (install) for each line item; include all applicable taxes.
- RRPL Insurance – Lump sum.
For further information or questions regarding the Request for Proposals or submittal of a proposal, please contact:
- Mike Mulnix, SKOL Roadmaster at mmulnix@watco.com; phone 620-330-7415
- Jerod Gofourth, Assistant SKOL Roadmaster at jgofourth@watco.com; phone 620-515-1809
- Cody McGee, Division Engineer at cody.mcgee@watco.com; phone 217-855-4107
Work Reporting
Daily work reports must be filled out and submitted to Mike Mulnix – SKOL Roadmaster, Jerod Gofourth – SKOL Asst. Roadmaster, and Cody McGee – Division Engineer. Those reports should include updates to project schedules, any delays and/or changes in the scope of work. A detailed summary report must be submitted upon the completion of the project.
Cody McGee
Division Engineer
Watco
Doc. No. 053006